The Iraqi Arab Contractors Company is building the Samawah Hospital conception in Samawa city. Covering 27 acres the hospital contains a capacity of 400 beds, gardens, interior roads, storage & medical staff buildings. The duration of construction is 3 years as accounted by Iraq Ministry of Health, and a total value of 149 million U.S.D

Client The Ministry of Health - IRA
Main Contractor German Medical Solutions (GMS)
IAC Contract Value 27,516,075 US Dollars
Duration 10 Months 
The amount of concrete 54,000 meter cubic

 